Stubbing Holme Road Flood Alleviation Scheme (FAS)

Additional government funding announced in 2019 for the Hebden Bridge FAS has meant that the Environment Agency (EA) has been able to revisit designs for the Stubbing Holme Road area, which had previously been put on hold.  The Stubbing Holme Road Flood Alleviation Scheme (FAS) is being developed as a separate project from the main Hebden Bridge FAS.

The Stubbing Holme Road FAS aims to improve protection to approximately 56 residential properties and 3 businesses.  

The Scheme

Stubbing Holme Road is at risk from flooding from the River Calder and Rochdale Canal.  It is located upstream of Hebden Bridge on the River Calder and includes a tributary, Colden Clough, which meets the Calder at a confluence by the Longstaff Court cul-de-sac.

The plans for the scheme include:

  • Raising and strengthening river walls along Stubbing Holme Road
  • Strengthening and isntalling walls along Rochdale canal to pass flows to the Hebden Bridge FAS canal overflow at the Vale Centre site
  • A flow diversion solution at Longstaff Court to return water to the river
  • Improving protection to riverside properties

Next Steps

In the coming months the EA will be carrying out detailed design activities which will involve surveys, site investigations and stakeholder engagement.

As we progress with the design, we now need to ensure that the scheme is cost beneficial and until the full scope of scheme is finalised, the costs will not be fully understood.   We cannot commence construction until costs have bben finalised and all funding secured.  Due to the complexity of the locations and proposed interventions, there may be risk of costs increasing. Whilst the current project costs include an allowance to address potential cost increases, the Environment Agency and Calderdale Council will continue to pursue additional funding sources, on top of those already secured to further mitigate against this risk.

Latest Information

Keeping You Informed - Ground Investigation Work - August 21

If you have any questions regarding any of the planned work in this area, please email HebdenBridgeFAS@environment-agency.gov.uk.